Complete project execution
35 days
16.04.12
1.06.12
1
Engineering
35 days
16.04.12
1.06.12
1.1
Project examination
1 day
16.04.12
16.04.12
1.2
Material specification
2 days
17.04.12
18.04.12
1.3
Material ordering
1 day
19.04.12
19.04.12
1.4
Equipment layouting
3 days
20.04.12
24.04.12
1.5
Supervision and meetings
27 days
25.04.12
31.05.12
1.6
Bill of works
1 day
1.06.12
1.06.12
2
Workshop
20 days
24.04.12
21.05.12
2.1
Project examination and material comparison
2 days
24.04.12
25.04.12
2.2
Preparing distribution boards
2 days
26.04.12
27.04.12
2.3
Mounting equipment
3 days
30.04.12
2.05.12
2.4
Wiring
10 days
3.05.12
16.05.12
2.5
Testing
2 days
17.05.12
18.05.12
2.6
Packaging
1 day
21.05.12
21.05.12
3
Field
31 days
19.04.12
31.05.12
3.1
Field preparations and digging
7 days
19.04.12
27.04.12
3.2
Cable laying
4 days
30.04.12
3.05.12
3.3
Installation laying
13 days
4.05.12
22.05.12
3.4
Mount distribution boards
1 day
23.05.12
23.05.12
3.5
Wiring distribution boards
4 days
24.05.12
29.05.12
3.6
Testing
2 days
30.05.12
31.05.12
Task Name
16 Apr 12
M
T
W
T
F
S
S
Duration
Start
ETA
23 Apr 12
M
T
W
T
F
S
S
30 Apr 12
M
T
W
T
F
S
S
7 May 12
M
T
W
T
F
S
S
14 May 12
M
T
W
T
F
S
S
21 May 12
M
T
W
T
F
S
S
28 May 12
M
T
W
T
F
S
S